ISB
Work in Progress
- Brick work along line 17, from B to G is in progress.
- Continue retaining wall along line 8.
- Continue curtain wall installation at the northeast side.
- Finalize pre cast and brick work along A line.
- Continue the pouring of the hydraulic slab on the east side, lines 14 to 17.
- CMU installation in penthouse completed.
- Start backfilling for slab on grade east side of the building, lines 14 to 11.
- Start Hydraulic slab on the east side of the building, lines 8 to 11.
- Start CMU wall in basement, lines 1 to 7.
Looking Forward
- Continue pre cast and brick work along line 17, from B to G.
- Pour Hydraulic slab on the east side of the building, lines 14 to 17.
- Finalize installation of the CMU in penthouse.
- Continue CMU wall in basement, lines 1 to 7.
- Continue hydraulic slab on the east side of the building, lines 8 to 11.
- Continue backfilling for slab on grade, east side of the building, lines 14 to 17.
Williams Hall
Work in Progress
- Continue piping work for steam station in mechanical room.
- Ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17 is in progress.
- Continue plumbing work for W3: roof drains, storm lines, etc..
- Continue electric rough installation in basement, and 2nd floor lines 1 to 17.
- Continue duct work installation in 1st floor east side of the building.
- Continue final painting concrete.
- Finalize drywall for W3.
- Finalize installation of steel for exhaust fans on roof for W3.
- Start painting walls for W3.
Looking Forward
- Continue piping work for steam station in mechanical room.
- Continue ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17.
- Continue plumbing work for W3.
- Continue electric rough installation in basement.
- Continue final painting concrete.
- Continue installation of mill work for W3.
- Continue fireproofing in penthouse and 2nd floor on the east side of the building.