ISB
Work in Progress
- Continue the work of water proofing mud mat on the east side of the building, lines 14 to 17.
- Continue framing roof work at east side of the building, and roofing work on the penthouse.
- Continue curtain wall installation at the northeast side.
- Continue backfilling for slab on grade from line 7 to 17.
- Continue pre cast and brick work along A line.
- Continue brick work along line 17, from B to G.
- Continue miscellaneous detailing work.
- Start Hydraulic slab on the east side, lines 14 to 17.
- Start retaining wall along line 8.
- Finalize concrete work for stair #3.
Looking Forward
- Continue pre cast and brick work along line 17, from B to G.
- Pour retaining wall along line 8.
- Pour Hydraulic slab on the east side of the building, lines 14 to 17.
- Start installation of the CMU in penthouse.
- Start backfilling for slab on grade, east side of the building, lines 14 to 17.
- Finalize pre cast and brick work along line A.
Williams Hall
Work in Progress
- Piping work for steam station in mechanical room is in progress.
- Continue ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17.
- Continue plumbing work for W3.
- Continue electric rough installation in basement.
- Continue final painting concrete.
- Start tapping drywall for W3.
- Installation of steel for exhaust fans on roof for W3 has begun.
- Finalize concrete repair work.
Looking Forward
- Continue piping work for steam station in mechanical room.
- Continue ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17.
- Continue plumbing work for W3.
- Continue electric rough installation in basement.
- Continue final painting concrete.
- Continue curtain wall installation.
- Start priming drywalls for W3.
- Start installation of mill work for W3.
- Start fireproofing in penthouse and 2nd floor on the east side of the building.